Project Name: Wood Lane

 
Project Reference Number: IMGD240019
Project Network: Cadent

Scheme background: Cadent completed Cut off and abandon 457m of 180mm / 125mm / 90mm gas mains to allow site to be redeveloped.

Thames waters were completing mains replacement for their asset.

Due to the location of the works, multiple parties were involved working within Thames waters tm (multiway signals).

The key proposal is that the existing approved Cadent permit (AZ5021001326942) is converted to collaborative permit led by Thames Water, extending the area under TM to the northern arm of the junction to accommodate their area, and continuing for a total of six weeks, with evolving collaboration between utility companies.

Key Parties involved London Borough of Hammersmith and Fulham (LBHF)The Project Centre (Design Consultant for LBHF), FM Conway (Junction Works Contractor for LBHF).

Cadent (Disconnection), Thames Water, UKPN, BT (Openreach), COLT (telecoms), Vodafone, Virgin Media, Adjacent Development Imperial (Developer), Medhurst Project Management (on behalf of Imperial), Careys (Contractor for private development)

Thames/ Morrison – 6 weeks including water to site.

  • JSM – 1ST Phase 2 days
  • Open Reach- 3 weeks
  • UKPN – 1st Phase LV 2 weeks
  • Vodafone / Virgin Media – 1st phase 1 week
  • Cadent - 7 days
  • Colt Telecoms – 7 days

GLA strategic importance criteria (if applicable):

  • 7 parties were involved in an evolving collaboration including telecoms company utilities and borough.
  •  Works undertaken outside white city underground station.
  • Heavy footfall
  • Works near Westway (A40)
  • Multiple business impacts
  • Buses impacted
Collaboration Partner(s):
Thames Water
Project Start Date:
5 May 2024
Length of Collaboration (Meters):
89.01m
Estimated Days Saved:
7
 
Local Authority:
London Borough of Hammersmith & Fulham
Project End Date:
25 May 2024
Level of Collaboration:
Level 2
Project Status:
Complete