Project Name: Wilmount Street
Scheme background: UK Power Networks (UKPN), SGN, and Thames Water collaborated to share a 70-metre trench, with UKPN managing the reinstatement work. This project is part of UKPN's 4km new connection initiative. SGN installed a new gas pipe for residents, while Thames Water conducted maintenance to reduce water leakage.
UKPN organised a meeting with the SGN and Thames Water and provided traffic management, reducing disruption for residents and businesses by 17 days.
Communication with Local Stakeholders
A communication plan was developed with the local authority, SGN, and Thames Water to highlight the benefits of this collaboration. UKPN handled traffic signage, while SGN informed residents with a letter drop before the project began.
UKPN Permit EC40080662494-01- 22 Jul - 3 Sep 44 days from the junction of North Woolwich Road to the junction of Masons Hill, WILMOUNT STREET, WOOLWICH 170m
Thames Water Permit MU704000032057309-001-01- 22 Jul - 26 Jul 5 days
SGN Permit XW0722364271-01621-02- 22 Jul - 2 Aug 12 days
The following is not a comprehensive list of the companies involved but does indicate some of the parties that had to be communicated with to keep the project on target:
- Greater London Authority (GLA)
- SGN
- JSM Utilities (SGNs contractor)
- UKPN
- Compass
- Thames Water
- Greenwich Council
- Local businesses