Project Name: Wilmount Street

 
Project Reference Number: 2364271
Project Network: SGN

Scheme background: UK Power Networks (UKPN), SGN, and Thames Water collaborated to share a 70-metre trench, with UKPN managing the reinstatement work. This project is part of UKPN's 4km new connection initiative. SGN installed a new gas pipe for residents, while Thames Water conducted maintenance to reduce water leakage.

UKPN organised a meeting with the SGN and Thames Water and provided traffic management, reducing disruption for residents and businesses by 17 days.

Communication with Local Stakeholders

A communication plan was developed with the local authority, SGN, and Thames Water to highlight the benefits of this collaboration. UKPN handled traffic signage, while SGN informed residents with a letter drop before the project began.

UKPN Permit EC40080662494-01- 22 Jul - 3 Sep 44 days from the junction of North Woolwich Road to the junction of Masons Hill,  WILMOUNT STREET, WOOLWICH 170m

Thames Water Permit MU704000032057309-001-01- 22 Jul - 26 Jul 5 days

SGN Permit XW0722364271-01621-02- 22 Jul - 2 Aug 12 days

The following is not a comprehensive list of the companies involved but does indicate some of the parties that had to be communicated with to keep the project on target:

  • Greater London Authority (GLA)
  • SGN
  • JSM Utilities (SGNs contractor)
  • UKPN
  • Compass
  • Thames Water
  • Greenwich Council
  • Local businesses
Collaboration Partner(s):
SGN, Thames Water and UKPN
Project Start Date:
22 July 2024
Length of Collaboration (Meters):
170m
Estimated Days Saved:
12
 
Local Authority:
Greenwich
Project End Date:
2 August 2024
Level of Collaboration:
Level 2
Project Status:
Complete