Project Name: Station Road
Scheme background: The project involved a collaboration between UK Power Networks (UKPN), SB Civil Engineering Ltd working on behalf of the London Borough of Barnet, Cadent, BT and Affinity Water working at Station Road West Hendon Broadway to Minimize disruption by 44 days.
Cadent - AZ5021001344184-06 16/09 -24/11 130m gas mains,50 working days (70 calendar days). Utility asset works 2 additional weeks in UKPNs permit (shared trench). Work restricted to agreed TM plans WAT-D00394
BT - BC991GEC-LWED-1342857-1-02 25/11-27/1, 3 working days (3 calendar days). Works description: Works to clear blockages and, if required, replace duct
BC410LO00000500344928202-01- 29/22/24-05/12/24, 5 working days (7 calendar days). Works description: Demolish 1 existing joint box(s) or cabinet base(s), Reposition 20m of duct (up to 4 poly ducts)
Affinity Water MX060005656LS_01-03- 30/10-22/11- 19/11/24,15 working days (21 calendar days). Works description: FH Relocation on behalf of Affinity Water - Permit in conjunction with MX060005656LS
UKPN - EC30001492447-02,18 Nov 2024 08:00:00 – 29 Nov 10 working days (12 calendar days).EC30011617296-01 18/11-2/12 20/01 second phase to complete works
GLA strategic importance criteria (if applicable):
- 2 planned public realm schemes
- 3B congestion,3c Public transport,
- 3D mosques and churches
- 3A schools and nursery
- Very high Pedestrian area