Scheme background: UKPN - Connections projects: disconnection / reconnection of existing electricity supply for a customer: 200 new connection, disconnection of old supply, where the primary promoter who provided the road closure for both Cadent Gas and Thames Water to work under.
Cadent Gas - Cadent to excavate and lay 63mm to welded cellar entry and 2m of 2" steel into hollow cellar.
Thames water - plot 1: 1x32mm, commercial metered supply off 4". existing commercial upgrade & disconnection. 2m footway 3m cw. as part of the agreement, Thames water.
GLA strategic importance criteria (if applicable):
- Opposite Liverpool Street – heavily influenced by footfall.
- Major Busy A10 road, works are located near junction leading to A10.
- Outside a Pub
- Traffic heavy due to the location near the station.